Commercial and Government
800 Waterford — Miami
- Date:November 2015 – April 2017
- Contract Amount:$1.7M
- Owner:WRC Properties, LLC
- General Contractor:Brasfield & Gorrie, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
Marina Palms North and South Tower — North Miami
- Date:March 2014 – January 2017
- Contract Amount:$4.0M
- Owner:Marina Palms, LLC
- General Contractor:Coastal Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, lift station, parking lot paving and roadway, concrete paving, curbing and walks, and striping and signage.
Miami Science Museum — Miami
- Date:March 2012 – December 2016
- Contract Amount:$1.8M
- Owner:Miami Science Frost Museum
- General Contractor:Skanska/Suffolk Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, lift station, parking lot paving and roadway, concrete paving, curbing and walks, and striping and signage.
Alta at Dadeland — Miami
- Date:January 2014 – September 2016
- Contract Amount:$1.0M
- Owner:Alta Dadeland Investors, LP
- General Contractor:Coastal Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
FIU Parking Garage 5&6 — Miami
- Date:October 2008 – December 2015
- Contract Amount:$3.5M
- Owner:Florida International University
- General Contractor:Turner & Fachina Construction
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
Dadeland Mall Expansion — Miami
- Date:February 2012 – April 2013
- Contract Amount:$1.9M
- Owner:Simon Properties LTD
- General Contractor:Coastal Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
MIC GMP 6-C Central Station — Miami
- Date:July 2011 – November 2014
- Contract Amount:$5.4M
- Owner:Florida Department of Transportation
- General Contractor:GC Turner Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
Infinity @ Brickell — Miami
- Date:May 2006 – July 2009
- Contract Amount:$1.3M
- Owner:Infinity at Brickell, LLC
- General Contractor:GC Hunt Construction, Inc.
Scope of work: Project highlights include the Structural Excavation, underground utilities, parking lot paving and roadway, curbing and walks, signalization and striping and signage.
W Hotel South Beach — Miami
- Date:November 2006 – October 2009
- Contract Amount:$2.9M
- Owner:2201 Collins Fee, LLC
- General Contractor:GC Plaza Construction, Inc.
Scope of work: Project highlights include the Structural Excavation, underground utilities, parking lot paving and roadway, curbing and walks, signalization and striping and signage.
Carrillon Condominiums — Miami
- Date:April 2005 April 2006
- Contract Amount:$2.9M
- Owner:The North Carrillon LLC
- General Contractor:GC Plaza Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, curbing and walks, and striping and signage.
U.S. Courthouse — Miami
- Date:February 2006 October 2007
- Contract Amount:$3.6M
- Owner:Federal General Service Admininstration
- General Contractor:Dick Corporation, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, lift station, curbing and walks.
RReef Warehouse Building — Miami
- Date:June 2005 July 2006
- Contract Amount:$2.9M
- Owner:CLP Industrial Properties
- General Contractor:Butters Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, highway lighting, lift station, curbing and walks, and landscaping.
Performing Arts Center — Miami
- Date:September 2001 — November 2004
- Contract Amount:$2.7M
- Owner:Miami Dade County
- General Contractor:Odebrecht Construction, Inc.
Scope of work: This project was for the Performing Arts Center site work. Major items of work included: clearing and grubbing, basement excavation, tunnel excavation, contaminated soil removal, structural excavation and backfill, cut and fill to subgrade for interior and exterior of Performing Arts Center.
DMS/FDLE Office Building — Miami
- Date:October 2001 July 2002
- Contract Amount:$2.6M
- Owner:State of Florida
- General Contractor:Centex-Rooney Construction, Inc.
Scope of work: Project highlights include the building pad construction, underground utilities, parking lot paving and roadway, highway lighting, lift station, curbing and walks, and landscaping as a subcontractor.
ABC Distributing — Opa Locka
- Date:1998 - 1999
- Contract Amount:$3.4M
- Owner:Miami Dade County Aviation
- General Contractor:Codina Constuction, Inc.
Scope of work: Project highlights include the filling approximately 100 acre site, building pad construction, underground utilities, paving and roadway as a subcontractor.
Dadeland Mall Expansion — Miami
- Date:1997 - 1998
- Contract Amount:$2.3M
- Owner:Simon Properties LTD
- General Contractor:Centex-Rooney Construction, Inc.
Scope of work: Project highlights include the parking structure modifications, underground utilities, parking lot paving and roadway, highway lighting, curbing and walks, and landscaping as a subcontractor. Multiphase construction in excess of 80 phases.
The Falls Shopping Center
- Date:1996 - 1997
- Contract Amount:$4.4M
- Owner:Related Group, Inc.
- General Contractor:M-P Contractors, Inc.
Scope of work: Project highlights include the reconstruction of 60 Acre parking lot, building pads, underground utilities as a subcontractor.